Minor projects

2 Result(s) Found

As part of Woollahra Council’s 2025/26 Infrastructure Works Program, Council’s contractor is upgrading the kerb, gutter and footpath at Cranbrook Road, between Carrington Avenue and Beresford Crescent, Bellevue Hill.

The works will improve pedestrian safety and local amenity.

Works include:

  • Upgrading the footpath.
  • Upgrading the kerb and gutters.
  • Upgrading kerb ramps at the intersection of Cranbrook Road and Carrington Avenue.

The work is scheduled to start on Monday 12 January 2026 and should be completed within 3 weeks, weather permitting.

They will be carried out between 7am - 5pm Monday to Friday, and 7am - 1pm on Saturday.

Note: Asphalt road pavement replacement will occur at a later date, during the school holidays. A separate notification will be issued for this work. 

 

10 December 2025 - Epping Reserve Project Update - The majority of works have been completed, with a small amount of landscaping remaining. Planting to be finalised in January 2026, to ensure establishment of plants. 

1 October 2025 - Kiaora Reserve Project Update - Works are now completed.

Council’s contractors will be undertaking improvement works in Kiaora Reserve and Epping Reserve, Double Bay in August and September 2025.

A new decomposed granite pathway will be constructed in Kiaora Reserve between the Sydney Water pumping station and the carpark adjacent to the Forest Road intersection. Interactive log stations will be installed alongside the new pathway, and in Epping Reserve to provide opportunities for informal play and informal seating. 

Works include:

  • A new decomposed granite path within the grassed area of Kiaora Reserve.
  • Tree works in Epping Reserve including tree pruning and removal of dead Robinia and overgrown Gymea Lilly.
  • Two replacement trees to be planted in Epping Reserve.
  • New landscaping and replanting garden beds in Epping Reserve.
  • Three timber play elements in Kiaora Reserve.
  • Three timber play elements in Epping Reserve.

Tree works and landscaping preparation works will commence in Epping Reserve from 20 August 2025.

The pathway works in Kiaora Reserve are scheduled to commence on Monday 1 September 2025. All works should be completed within 3-4 weeks, weather permitting.

The scheduled works will be carried out between 7am - 5pm Monday to Friday, and 7am – 1pm on Saturday. 

Page 1 of 1

Search